There is “an increasing risk” of danger to local shipping if Ireland’s only offshore windfarm is left in its current condition, its operators have warned, as it seeks to dismantle the two-decade-old turbines.
Phase 1 of the Arklow Bank windfarm opened in 2005. Its operators are now seeking planning permission to dismantle the site and remove the degrading components still in place.
The overarching priority for the operators is that “it does not cause harm to people, vessels or marine life”, Arklow Energy said.
The seven-turbine project ceased generating electricity for the grid two years ago due to safety concerns.
READ MORE
Annual accounts lodged with the Companies Office by windfarm operator Arklow Energy Ltd (AEL) for the years from 2004 to 2024 show that the project – located 10km off the Co Wicklow coast – generated cumulative revenues of €133 million across its operational life.
A planning report with the decommissioning application lodged with An Coimisiún Pleanála (ACP) states that during its operational period, the Arklow Bank wind farm generated 1.29GWh of renewable energy, or the equivalent of enough electricity to power about 850,000 households.
In a cover letter lodged with the application, director Jerry Barnes at planning consultants MacCabe Durney Barnes, for the applicants, said AEL’s “overarching priority is to ensure that Arklow Bank Wind-farm Project Phase I does not cause harm to people, vessels or marine life”.
[ Winds of change: Unnerving times for Ireland's offshore energy investorsOpens in new window ]
Barnes warned that if the infrastructure is left in situ and continues to deteriorate, “there is an increasing risk of collision from falling debris, including the potential for debris to wash up on the coast”.
Barnes told ACP the continuing degradation of the wind-firm “poses an increasing risk to the safety of the maritime area”.
Preliminary results of an engineering review indicate that the degradation will increase exponentially beyond 2027, he added. He said the decommissioning works are therefore necessary to safeguard the maritime area.
AEL “is concerned that the continuing degradation of the infrastructure may lead to pollution in the maritime area,” he said, adding that if AEL is able to secure consent during the first half of 2027, it may be able to execute works offshore during 2028.
He said that while AEL – a subsidiary of global energy company GE Vernova Inc – understands that due process must be followed, “we would respectfully urge the commission to process this application as expeditiously as possible”.
A planning report lodged with the application stated that a maintenance campaign in 2025 resulted in the removal of the blades from the turbines.
[ Marine environmental situation is stark, Oireachtas committee toldOpens in new window ]
Accounts filed for AEL show that it made a provision of €13.7 million for the blade maintenance campaign works in its 2024 accounts.
The applicants are seeking planning permission to June 19th 2033 to facilitate programming of the proposed works offshore.












