Minister for Health says current handover date of October 2024 is being reviewed
BAM
Articles realted to the BAM construction company
Project delivery team to appear before Dáil’s Public Accounts Committee in attempt to explain cost overruns and delays
Dáil due to get new ‘guidance’ this week on timeframe for completing building
Court dispute in June heard contractor is in dispute over claims valued at hundreds of millions of euro
Minister for Health Stephen Donnelly has announced a number of appointments and reappointments to the board
Documents also reveal that more than 300 doors in the hospital may have to be replaced or demolished
Corporate-intelligence firm with global reach regularly employed by multinationals and governments
Application for case to return to fast-track list was made by lawyers for the contractor after intensive talks over 18 months ‘broke down’
Minister for Health accuses Sinn Féin of ‘playing politics’, saying providing estimated cost could open State to further claims
The chief officer of the board will cite examples of the developer’s low productivity and its failure to provide monthly progress reports
The Government will get its ‘grand projet’ but future generations will be saddled with the cost of paying for it
Contractor BAM issued a report in February citing a ‘substantial completion date’ of May 2024, instead of March which was stated in a previous report
Inside Politics: Any suggestion NCH might cost more, or more importantly, open late, retains the whiff of political cordite
New children's hospital faces issues relating to the layout of ventilation systems in theatres that could add millions to its cost and add months to the delivery