How pretty much zilch has been done at Ground Zero eight years on from 9/11

Plans to rebuild the Twin Towers have been beset by delays, cost over-runs and feuding, writes KEITH RICHBURG

Plans to rebuild the Twin Towers have been beset by delays, cost over-runs and feuding, writes KEITH RICHBURG

IN THE aftermath of the September 11th, 2001, attacks, with the ruins of the World Trade Centre still smouldering, political leaders – from New York mayor Rudolph Giuliani to president George W Bush – vowed to quickly rebuild the site, bigger and better than before.

“The skyline will be made whole again,” Mr Giuliani said. And as a sign of the city’s resilience, initial plans called for the rebuilding to be complete by 2011 – the 10th anniversary of the attacks.

Eight years later, the site known as “Ground Zero” remains mostly a giant hole in the ground. A projected completion date has been pushed back years, if not decades.

READ MORE

The project has been beset by repeated delays, changing designs, billions of dollars in cost over-runs, and feuding among the various parties involved.

“It’s just one big political nightmare,” said Jim Riches, a retired New York deputy fire chief, who lost his firefighter son, Jimmy, on 9/11 and who has attended meetings on the progress of the construction. “I think it’s a national disgrace . . . We can put a man on the moon, but we can’t get all the politicians in New York . . . to build the World Trade Centre back up again.”

What happened over the past eight years is a story of grandiose plans clashing with practical realities; of the flush of early emotions giving way to cold, financial calculus; of public officials fighting with a private developer; and of bureaucrats battling one another at almost every level with no one really in charge.

“Nobody wants to accept responsibility,” said former New York mayor Ed Koch. He joined others in laying blame before two chief agencies: the Port Authority of New York and New Jersey, which owns the land; and the Lower Manhattan Development Corp, which was created to channel all federal aid pouring in.

“It’s shameful that they have failed in their responsibility to build this in a measured and responsible way,” Mr Koch said.

A sad symbol of the slow progress is the former Deutsche Bank building, next to where the Twin Towers stood. The 40-storey building was heavily damaged by the collapse of the World Trade Centre’s south tower and was declared uninhabitable.

Eight years later, the building still has not been torn down: two firefighters died in a blaze in the building in 2007, suspending the deconstruction, and the discovery of toxic dust inside – with asbestos, lead and other dangerous chemicals – has caused further delays.

Rebuilding the World Trade Centre site was always going to be an extremely complex undertaking. At 16 acres, it is larger than the downtown of many other American cities. It sits atop the intersection of several major city subway lines and a commuter train line to New Jersey.

Its location in a densely packed part of Lower Manhattan makes it difficult for construction crews to work, while its proximity to City Hall, police headquarters and the federal courts prompts security concerns. The initial reaction after the attacks was to rebuild the towers exactly as they were. But some insisted the footprints of the original towers be left untouched, out of respect for those who died.

Residents of Lower Manhattan and developers, meanwhile, envisioned adding retail shops to the vast expanse of office space that made up the towers. A 2005 design called for a spiralling glass skyscraper, named Freedom Tower, that would rise a symbolic 1,776ft in the air (the year the American Declaration of Independence was signed). But after the design was unveiled, the New York Police Department said the new building would be too vulnerable to truck-bomb attacks and sent the architects back to the drawing board. A redesign moved the tower back from the street and placed it atop an impregnable 200-foot steel-and-concrete base.

Then, this year, the name was changed to World Trade Centre One, out of fears that Freedom Tower would become too tempting a target for terrorism.

The plan now calls for four office towers, including World Trade Centre One, with a memorial and two tree-lined reflecting pools standing on the footprints where the old twin towers stood. Cascading waterfalls lead down to a subterranean museum, 70ft below ground level. The plan also includes a massive, futuristic-looking transportation hub.

The projected costs have soared far above the $15 billion budget, construction is years behind schedule, and the developer of three towers, Larry Silverstein, is locked in a dispute over financing with the Port Authority.

Mr Silverstein wants the Port Authority to back loans to build two of the towers. He has blamed the authority’s delays for costing him crucial financing, since private backing became hard to find after credit markets froze last year.

Alan Gerson, the city council member whose district includes Ground Zero, said, “We’re mad as hell, and getting madder at the prospect of additional delay.” He said that “the site needs a sheriff” to oversee the various agencies, mediate disputes, and solve engineering and financial problems.

Independent mayor Michael Bloomberg unsuccessfully tried over the summer to mediate the dispute between Silverstein and the Port Authority. He later issued a tough statement that blasted the impasse and the resulting delay as “unacceptable” and “intolerable”.

As time has passed since the 2001 attacks, some are now questioning the complexity of the plan. Others are wondering whether a city hit hard by the recession – with a shrunken financial sector and a glut of cheap commercial space – really needs to be spending billions on office space.

"The design of that site was done in a political and emotional environment," said Kathryn Wylde, president of the Partnership for New York City, a nonprofit business group. "It wasn't realistic about the technical aspects and the cost, and it wasn't realistic about anticipating that this was a long-term project that would have to go through changes." – ( The Washington Post)