HSE postpones promised new cystic fibrosis patients' facility

A PROMISE by the Health Service Executive that a brand new building with state of the art accommodation for cystic fibrosis (…

A PROMISE by the Health Service Executive that a brand new building with state of the art accommodation for cystic fibrosis (CF) patients would be provided at Dublin’s St Vincent’s hospital by 2010 is not now going to be honoured, it has emerged.

The HSE has confirmed that funding for constructing the building which would have about 30 single rooms for CF patients will not be available “until 2011 at the earliest”.

Godfrey Fletcher, the chief executive of the Cystic Fibrosis Association of Ireland, said the news was a major slap in the face for patients who have long campaigned for better facilities.

CF patients are prone to picking up infections and as a result should be accommodated in single ensuite rooms. After an outcry over the lack of isolation facilities for CF patients at St Vincent’s, which is the national adult referral centre for the condition, in early 2008 the HSE came up with an interim solution. It said 14 single rooms would be provided while a new block at St Vincent’s with a total of 120 beds – about 30 of which would be for CF patients – was being built. It said it would be ready by 2010.

READ MORE

However, HSE replies to written questions from members of the Oireachtas Health Committee, distributed this week, show that not only has the new block been delayed, but only eight of the 14 single rooms as part of the interim solution have been delivered on.

“The HSE had intended in early 2008 that another area of the hospital could also be reconfigured to provide an additional six single rooms on an interim basis. It has not yet been possible to realise this proposal due to other pressures at the hospital which required the use of the intended area as a decant facility to enable other essential capital works,” the HSE said in its written reply. “Design work and preparation of tender documents continues in respect of the proposed new ward block . . . the HSE’s capital plan shows that capital for construction, however, would not be available until 2011 at the earliest,” it added.

Mr Fletcher said the eight single rooms provided last August were very welcome and already patients using them were recuperating much faster. But the news that there would not be money even to start the new block until 2011 had come as a great shock to his organisation, he said.

“We were under the impression that it was to be a quick-build contract to be completed by 2010.” The fact that it was not was very serious, particularly when all the promised interim beds had not even been provided, he said. He predicted his members would be “rioting on the streets” if the promised single rooms were not forthcoming.

The lack of isolation facilities at the hospital for CF patients was condemned in a 2005 report by UK consultant Dr Ronnie Pollock. It said the lack of segregation and isolation for CF patients was dangerous and there was a risk patients who picked up infections would sue. It noted that Ireland has the highest incidence of CF of all European countries and there were “also strong indications that outcomes in Ireland are worse”.